Work out how much concrete a slab, footing, sonotube, set of stairs or curb needs, in cubic yards, cubic feet and bags to buy. Enter feet and inches instead of decimals, set your own overage, and see the point where ready-mix delivery beats mixing bags.

Choose what you are pouring

DimensionsSlab

qty

Reading your entry.

Slab Plan1:SCALE

The drawing redraws to your real proportions as you type. Dimension lines carry the exact values you entered.

Concrete NeededLIVE

Order this much, overage included

0.00 cubic yards

0.00 cu ft · 0.00 cu m

Base volume0.00 cu yd
Overage added at 10%0.00 cu yd
Total to order0.00 cu yd
Cubic yards
0.00
Cubic feet
0.00
Cubic meters
0.00

Overage allowance

%

The overage is shown on its own line above and is never folded into the base figure. Use 5% to 10% for a formed slab on flat, compacted base, and 10% to 15% where the subgrade is soft, uneven or hand dug, because the extra depth all goes underground where you cannot see it.

Bags To BuyROUNDED UP

40 lb bags
0
0.30 cu ft each
90 per cubic yard
60 lb bags
0
0.45 cu ft each
60 per cubic yard
80 lb bags
0
0.60 cu ft each
45 per cubic yard
Bags or ready-mix?Enter your dimensions and this line will tell you which way to go.

The honest crossover: bags win for small pours, ready-mix wins for big ones, and the line sits at roughly half a cubic yard, which is about 23 eighty-pound bags. Below that you are buying convenience. Above it you are buying a whole afternoon of mixing, so the delivery truck is usually cheaper once you count your own time and a rented mixer.

Two things to check before you call a plant: most have a minimum order, often one cubic yard, and most add a short-load fee on anything under about three to five yards. Both vary a lot by region and by plant, so ask for the number rather than assuming. Get current pricing on our concrete cost per yard page.

How This Is CalculatedSHOW THE WORKING

Enter dimensions and the full working appears here.

Every shape reduces to the same idea: get the volume in cubic feet, then divide by 27, because 1 cubic yard = 27 cubic feet (3 ft x 3 ft x 3 ft).

  • Slab and footing: length x width x thickness, with the thickness converted from inches to feet.
  • Column or sonotube: pi x radius squared x height. A 12 in tube has a 6 in radius, which is 0.5 ft.
  • Stairs: rise x run x N x (N + 1) / 2 x width, for N steps. This assumes a solid block poured down to grade. If you are forming over compacted fill or the stairs are open underneath, you need less.
  • Curb: (curb height x curb width) plus (gutter width x gutter thickness), times the run.

Bag yields are the figures the manufacturers print on the bag: 0.30 cu ft for a 40 lb bag, 0.45 cu ft for 60 lb, and 0.60 cu ft for 80 lb. Multiply out and 45 x 80 lb gives exactly 27 cu ft, one cubic yard. Note this is a yield figure, not a weight figure. Cured concrete weighs roughly 4,000 lb per cubic yard, more than the 3,600 lb of dry bag mix, because you add water.

Materials Ticket#CONC

homeprojectresources.com, Concrete Calculator
Enter dimensions to build your ticket.

Take the ticket to the yard or read it to the dispatcher. The TOTAL TO ORDER line already includes your overage.

Concrete Quick Reference

Cubic yards for a slab, by area and thickness
Slab area4 in thick5 in thick6 in thick
50 sq ft0.620.770.93
100 sq ft1.231.541.85
144 sq ft (12 x 12)1.782.222.67
200 sq ft2.473.093.70
300 sq ft3.704.635.56
400 sq ft (20 x 20)4.946.177.41
500 sq ft6.177.729.26
Bags per cubic yard, and what a bag covers
Bag sizeYieldPer cu ydCovers at 4 in
40 lb0.30 cu ft90 bags0.90 sq ft
60 lb0.45 cu ft60 bags1.35 sq ft
80 lb0.60 cu ft45 bags1.80 sq ft
Common pours, at a glance
JobTypical sizeCubic yards80 lb bags
Fence post hole10 in dia x 3 ft, each0.063
Deck footing (sonotube)12 in dia x 4 ft, each0.126
AC pad3 x 3 ft x 4 in0.115
Shed pad10 x 12 ft x 4 in1.4867
Single-car driveway10 x 20 ft x 4 in2.47112
Two-car garage floor20 x 20 ft x 4 in4.94223
Strip footing16 in x 8 in x 40 ft1.3260

Bag counts in these tables are the raw volume with no overage. Add your own allowance on top. Anything over about 23 bags is where most people stop bagging and start calling a plant.

Related Calculators

Concrete Calculator FAQ

How many 80 lb bags make a cubic yard?

45 bags. An 80 lb bag of standard concrete mix yields 0.60 cubic feet, and a cubic yard is 27 cubic feet, so 27 divided by 0.60 is exactly 45. For the other common sizes it is 60 bags at 60 lb (0.45 cu ft each) and 90 bags at 40 lb (0.30 cu ft each).

Those yields are the manufacturers' own printed figures and they are consistent across the major brands. They are yields, not weights: 45 x 80 lb is 3,600 lb of dry mix, while a cured cubic yard weighs closer to 4,000 lb, because you add roughly three to four quarts of water per 80 lb bag.

At what point should I stop buying bags and order ready-mix?

Around half a cubic yard, which is 13.5 cubic feet or about 23 eighty-pound bags. Under that, bags are simpler: no minimum order, no delivery window, no truck on your driveway, and you can pour in stages.

Over that, the math turns. Twenty-three bags is 1,840 lb to lift twice, plus a rented mixer, plus the very real risk of a cold joint if you cannot keep up with your own pour. Ready-mix arrives in one load at a consistent mix design. The catch is that plants usually have a minimum order, often one cubic yard, and a short-load fee below roughly three to five yards. Those numbers vary by region and by plant, so call two and compare rather than trusting a national average.

How thick should a concrete slab be?

The common residential figures are 4 inches for a patio, shed pad, sidewalk or standard garage floor, and 5 to 6 inches where vehicles heavier than a car will sit, such as a driveway used by a truck or RV, or a garage with a lift.

Thickness is only half the answer. A 4 inch slab on a poorly compacted base cracks faster than a 4 inch slab on 4 inches of compacted crushed stone. Your local building department sets the requirement for anything structural, including footing depth below the frost line, and that requirement wins over any figure on a website. Check before you order.

Why do concrete calculators give different answers for the same slab?

Almost always because of hidden overage. Some calculators quietly add 5% or 10% to the volume and show you only the final number, so their figure looks bigger than the raw geometry. Others round the cubic yards up to the next quarter yard, which is how plants actually sell it, without saying so.

The geometry itself is not in dispute: a 20 ft x 20 ft slab at 4 inches is 400 sq ft x 0.3333 ft = 133.33 cubic feet, and 133.33 / 27 = 4.94 cubic yards. Every honest calculator gets 4.94. This page shows the base volume, the overage and the total as three separate lines so you can see which number you are looking at.

How much concrete do I need per fence post?

For a common 4x4 post in a 10 inch diameter hole dug 3 feet deep, the hole holds about 1.64 cubic feet. Subtract the volume the post itself takes up, roughly 0.29 cubic feet for a 4x4 at 3 feet, and you are near 1.35 cubic feet of concrete, which is about 3 eighty-pound bags per post.

Use the Column / Tube mode above with your real hole diameter and depth, and set the quantity to your number of posts. This calculator gives you the full hole volume, so treat it as a slight over-estimate for posts, which is the direction you want to be wrong in.

Does the calculator account for rebar, mesh or a vapor barrier?

No, and it should not. Rebar and welded wire mesh displace a fraction of a percent of the volume, which is far smaller than the variation in your actual excavated depth. A vapor barrier sits under the slab and displaces nothing.

The real variable is the subgrade. A slab formed at a nominal 4 inches over a hand-dug base routinely comes out at 4.5 inches in places, and that alone is a 12% increase in volume. That is what the overage line is for, and it is why the allowance should go up when the base is rough.

How do I calculate concrete for stairs?

Use the Stairs mode. The formula for a solid poured staircase with N steps is rise x run x N x (N + 1) / 2 x width. For 4 steps at a 7 inch rise and an 11 inch run, 4 feet wide, that is 0.583 x 0.917 x 10 x 4 = 21.39 cubic feet, or 0.79 cubic yards.

The assumption baked into that formula is a solid block poured down to grade. If your stairs sit on compacted fill, are formed over a void, or are cantilevered from a wall, you need less, sometimes far less. Measure what you are actually filling and use the slab or footing mode for the pieces if the shape is unusual.

What is a sonotube and how do I size the concrete for one?

A sonotube is a cardboard forming tube used for round footings and pier columns. It is sold by inside diameter, commonly 8, 10, 12, 16 and 18 inches. The concrete volume is simply the volume of the cylinder: pi x radius squared x height.

A 12 inch tube has a 6 inch radius, which is 0.5 ft, so each foot of height takes 0.785 cubic feet. A 4 foot tube holds 3.14 cubic feet, about 0.12 cubic yards or 6 eighty-pound bags. Remember to measure the full height including the part below grade, and check your local frost depth requirement before you dig.